Although the Government of Nepal completed its preliminary obligations—including site clearance and the relocation of utility poles, drinking water pipelines, and internet cables—roughly four years ago, the Chinese side responsible for executing the project has failed to deliver the DPR. According to Department of Roads (DoR) officials, the project remains trapped in a cycle of repeated studies and unfulfilled deadlines, leaving the actual start date completely uncertain.
Broken Deadlines and Design Revisions A technical team from China’s Henan Communications Planning and Design Institute Company initially visited the site in Falgun 2079 (early 2023) and pledged to complete the DPR within two months. That deadline passed without progress. Following further delays, another Chinese technical team conducted a fresh field survey on July 6, 2025, promising to submit the report within three months—a commitment that has also gone unfulfilled.
DoR officials attribute much of the stall to ongoing design revisions. The Chinese side has struggled to finalize the placement of culverts, bridges, and proposed overhead bridges at three locations. Furthermore, prolonged debates over how to widen the road without compromising the archaeological heritage near the Swayambhu Temple have forced repeated restudies. Learning from technical and managerial hurdles encountered during the first phase of expansion from Kalanki to Koteshwar, China is reportedly taking extra time on planning, though the years-long wait has cast doubt on the project's overall implementation.
Scope Narrowed to Undisputed Section While the second phase was originally envisioned to stretch from Kalanki to Dhobikhola in Chabahil, China has expressed interest in expanding only the undisputed 9-kilometer stretch from Kalanki to Basundhara Chowk.
Site clearance between Narayangopal Chowk in Maharajgunj and Dhobikhola has been blocked by local resistance, as the expansion requires demolishing structures within roughly two meters of the road. Because the Kalanki–Basundhara corridor is fully cleared and the DoR has already moved forward with service lanes on both sides, the Chinese side is looking to prioritize the section ready for immediate work.
Awaiting Diplomatic Push Proposed to be built under a Chinese government grant at an estimated cost of Rs 6 billion (note: preliminary figures vary in reporting between Rs 600 million and Rs 6 billion), the project places full responsibility for the DPR, contractor selection, supervision, and construction materials on China.
Despite the formation of a new government led by Balendra Shah six months ago, observers note that no concrete diplomatic or technical breakthrough has been achieved to break the deadlock. Without a firm timeline from Kathmandu and Beijing, a project critical to easing the capital's worsening traffic congestion risks remaining confined to paper for years to come.