Previously, residents and businesses in the valley relied entirely on local micro-hydroelectric projects. With the completion of new transmission and distribution infrastructure, electricity supply began Thursday via an 11 kV feeder extended from the newly constructed 132 kV Burtiwang substation through Navi to Chhentung.
The power supply is routed through a 132 kV transmission line stretching from Motipur in Kapilvastu through Sandhikharka (Arghakhanchi), Tamghas, and Paundiyamarai to Burtiwang. Following the feeder's activation, approximately 13 distribution transformers covering Wowang, Phaleghar, Deurali, Navi, and Chhentung have been charged.
NEA officials expect the grid connection to eliminate chronic low-voltage issues while improving the regularity and quality of power across the valley. The authority noted that a stable electricity supply will directly support local households, boost tourism enterprises, and accelerate broader socio-economic activity in the area.
According to Dilip Maraseni, Chief of the NEA Baglung Distribution Center, residents can now apply for new grid connections at any time through the Burtiwang "No Light" office.
With Dhorpatan connected, Nisildhor in Nisikhola Rural Municipality-5 remains the only area in Baglung district yet to be linked to the national grid. Maraseni confirmed that the budget for Nisildhor’s electrification has already been allocated for the current fiscal year, and the contracting process is moving forward to achieve full district-wide grid coverage.