Rasuwagadhi Hydro Project Sees Delay

Sep 30, 2021 12:04 PM RSS



The under-construction Rasuwagadhi hydropower project has witnessed delay in the installation of equipment due to sheer ignorance on part of the contractor company.

No equipment has been so far installed in the power house due to dillydally of VOITH India, an Indian Company responsible for equipment placement.

Hydropower Project Chief Chhabi Gaire shared that they have repeatedly following up the Indian company to comply with the memorandum of understanding.

The company was entrusted with the responsibility to accomplish the given works, including import and installation of equipment at the contracted amount of Rs 2.8 billion.

The 111-MW project requires a year-long time for installing the equipment in power house and so far 50 percent of the progress has to be made. However, it has resulted in delay in the production of power from the project due to negligence of the contractor.

The equipment to be installed in the power house have been already stored in the project site and the installation would take momentum once the technical human resources are available. 




Gold Price Gains, Silver Declines for 2nd Day

Aug 24, 2026 10:44 AM

The gold price has increased while the silver price has decreased for second day on August 24.

Gold and Silver Price Decline

Aug 25, 2026 10:41 AM

Gold Price Gains, Silver Declines

Aug 23, 2026 10:58 AM