Tanahun hydropower project sees above 50 per cent progress

Oct 20, 2024 10:53 AM Merolagani



The Tanahun hydropower project with a capacity of 140 MW has achieved a progress of 58.1 percent.   

The work on the hydel is being carried out in three package, and 52.07 percent financial progress has been achieved, said project chief Shyamji Bhandari.   

Likewise, 35 percent progress has been made in the construction of structures including dams under package-1. 59 percent progress in the construction of power plants under package-2 and 73.5 percent of the construction of transmission line under package-3.   

The goal is to complete the project in the next two years, by Asar 2083 BS. The supply, installation and operation of hydromechanics and electromechanical equipment, as well as the construction of tunnels and powerhouses are underway.

Under package-3, the KEC International company of India is constructing a 220 kV double circuit transmission line from Damauli to Bharatpur in Chitwan. (RSS)  




Stock Market to Open on Wednesday

Sep 15, 2025 04:52 PM

The stock market which remained close from September 9 due to Gen Z movement is set to open on September 17.

Gold and Silver  Price Decline

Sep 17, 2025 10:45 AM