Construction of Rasuwagadhi power house in full swing

Nov 19, 2018 RSS

The construction of powerhouse of Rasuwagadhi Hydropower Project in Rasuwa has gained momentum.

The 4,185-metre-long redress tunnel of the 111-MW hydropower project has been already constructed. Likewise, the excavation works have also been carried out in power generation site and the construction of power house structure is gaining momentum, shared Project Chief Chhabi Gaire.

The project that began in 2014 has seen the overall progress of 70 per cent in its construction works, said Madhav Koirala, managing director of the project.

The hydropower company has the target to complete the construction of the project and generate the electricity by February 2020. Having a total estimated investment of Rs 13.64 billion, the project initially was expected to compete by 2017. The shortage of fuel caused by economic blockade and 2015 devastating earthquake as well as its aftershocks delayed the construction of the project.

As part of its drive for bio-diversity conservation, the project has planted 2,700 saplings in the project site and also constructed a building of Langtang National Park in Dhunche. ---

comments powered by Disqus

Development Banks Record Minimal Degrowth

Apr 24, 2024 06:56 AM

The net profit of development banks has declined less compared to commercial banks and finance companies in the third quarter.

Gold and Silver Price Decline

Apr 25, 2024 10:37 AM

Chirkhwa Hydropower Incurs Loss

Apr 25, 2024 09:26 AM